Contact Energy Project Columbus
Project Columbus involved new productions wells WK270, WK271 & WK272 in the Te Mihi Steamfield. The well controls integrated into the existing Te...
Project Columbus involved new productions wells WK270, WK271 & WK272 in the Te Mihi Steamfield. The well controls integrated into the existing Te...
Automation and monitoring of the TAU fuel storage facility including bulk tanker delivery, automatic day tank transfer, bulk and day tank level monitoring,...
Calcite Dosing Plants at various Contact Energy Geothermal sites in the Te Huka, Te Mihi and Ohaaki Steamfields. McMahon Involvement Electrical and controls hardware...
Lower Huia Pump Station with four pumps operating, is capable of supplying 60 million litres per day (MLD) to Huia Water Treatment Plant...
Hobbs Bay Wastewater Pump Station is a critical transmission pump station in the Watercare Orewa and Whangaparoa wastewater catchment area being the last...
Stage 1 electrical upgrade of the digester area at the Mangere wastewater treatment plant with the installation of supplies and switchgear to enable testing, commissioning...
The Kawakawa Bay wastewater treatment plant and vacuum pump station replaced an aging sceptic tank system that caused considerable pollution to the Kawakawa...
Huntly Power Station Coal Handling McMahon Involvement McMahon were engaged to design the replacement coal handling and bunker switchboards at Huntly Power Station. This included planning...
Tamavua and Waila Water Treatment Plants Suva Fiji McMahon Involvement Project investigation, scoping and cost estimates Upgrade of the Tamavua and Waila water treatment...
Electrical, instrumentation and control design for the upgrade of the Te Aroha Wastewater Treatment Plant McMahon Involvement Electrical, control and instrumentation design Control software...